A425 Update May 21

  • Tweet
Friday, 28 May, 2021
Jeremy Wright

The full closure of the A425 to allow HS2 works was originally intended to last 9 months and the subsequent proposal to extend that closure very substantially would have caused very significant disruption and damage to the local economy. I and local government colleagues argued consistently that this extension could not be justified and that earlier promises to build an offline diversion that would keep A425 traffic moving should be honoured. I am pleased to hear today that this is what HS2 Ltd and its contractors intend to do and that the full closure will be kept to the period originally suggested.

  • Articles

You may also be interested in

Lighthorne

Lighthorne Path Opening

Thursday, 11 August, 2022

It was a pleasure to officially open the Lighthorne Path to the community.

With thanks to Severn Trent Community Fund and to many local volunteers for helping make this happen.

HS2

  • HS2 Minister Visit
  • A425 Updates
    • A425 Update May 21
    • A425 Update April 21
    • A425
  • HS2 Long Itchington Tunnel Visit
  • HS2 in Warwickshire Commonplace Website
  • HS2 Natural England Licenses
  • HS2 Construction Commissioner Visit
  • Sir Mark Worthington - Constituency Tour
  • HS2 February 2020
  • HS2 Review Group Letter to Prime Minister December 2019
  • HS2 Sub Forum Meeting - October 2019
  • Ancient Woodlands Updates
  • Meeting with The Woodland Trust - October 2019
  • Submissions to the Oakervee Panel - Jeremy Wright MP - September 2019
  • Cubbington Woods Guided Walk and Picnic - September 2019
  • HS2 Statement - Cubbington Wood - September 2019
  • Cubbington Pear Tree and Meeting with the Transport Minister - September 2019
  • Views on HS2 September 2019
  • Second HS2 Forum Meeting - 5 July 2019
  • Meeting with Sir Mark Worthington (HS2 Construction Commissioner) – April 2019
  • First HS2 Forum Meeting - 15 March 2019
  • Kenilworth & Southam HS2 Implementation Forum
  • Letter to Simon Kirby, Chief Executive of HS2 Ltd
  • HS2 Third Reading
  • Follow-up inquiry on PHSO investigation into HS2 complaints
  • High Speed Rail Select Committee 2016
  • Petition to AP4 of the HS2 Hybrid Bill
  • Petition to AP2 of the HS2 Hybrid Bill
  • High Speed Rail Select Committee
  • High Speed Rail Bill Petition
  • HS2 Property Consultation September 2014
  • Abstaining on HS2 Hybrid Bill Second Reading
  • Second HS2 letter - October 2012
  • First HS2 letter - October 2012

Show only

  • Articles
  • Local News
  • Media
  • Opinions
  • Westminster News

Jeremy Wright MP for Kenilworth and Southam

Footer

  • About RSS
  • Accessibility
  • Cookies
  • Privacy
  • About Jeremy
  • About the constituency
  • In Parliament
  • Surgeries
ConservativesThis website is funded by the Independent Parliamentary Standards Authority (IPSA) for the purpose of assisting Jeremy Wright MP in the performance of their Parliamentary duties
Copyright 2022 Jeremy Wright MP for Kenilworth and Southam. All rights reserved.
Powered by Bluetree